(10) Position clamp (10) on tension load cell cable (4).
(11) Install clamp (10) on boom stud (11) with washer (12),
lockwasher (13), and nut (14).
(12) Install two preformed packings (15) on fittings (16).
(13) Connect two hydraulic hoses (17) to fittings (16).
(14) Install preformed packing (18) on check valve (19).
(15) Connect hydraulic hose (20) to check valve (19).
NOTE
Install plastic cable ties as required.
(16) Install tension load cell connector (21) on overload
shutdown box (22).
(17) Install proximity sensor connector (23) on overload
shutdown box (22).
16-85