TM 9-2320-366-34-3
16-3. M1084/M1086 BOOM ASSEMBLY REPLACEMENT (CONT)
(22) Route overload lockout connector (24) over top of
tension link cylinder (5) and RH lift cylinder (10).
(23) Route hydraulic hose (25) over top of tension link
cylinder (5) and RH lift cylinder (10).
NOTE
Install plastic cable ties and cable clamps as
required.
(24) Connect overload lockout connector (24) to top
connection on overload shutdown box (26).
(25) Connect hydraulic hose (25) on right side of boom
assembly (1).
c. Follow-on Maintenance.
(1) Connect batteries (TM 9-2320-366-20-3).
(2) Install hoist cable (TM 9-2320-366-20-5)
(3) Lubricate MHC (TM 9-2320-366-20).
(4) Perform crane load test (para 16-31).
End of Task.
16-18