TM 9-2320-366-34-4
NOTE
Perform steps (36) through (38) if PTO cover
was removed.
(36) Position PTO cover (32) and gasket (33) on torque
converter housing (23).
(37) Position 10 bolts (34) in PTO cover (32).
(38) Tighten 10 bolts (34) to 42-50 lb-ft (57-68 N·m).
d. Follow-On Maintenance.
(1) Install torque converter (para 7-2).
(2) Install control valve module (para 7-10).
(3) Install scavenge assembly pump (7-16).
(4) Install transfer case module (para 22-2).
(5) Demount transmission from maintenance stand
(para 7-5).
End of Task.
21-13