(11) Install two preformed packings (13) on fittings (14).
(12) Install two preformed packings (15) on fittings (16).
(13) Connect hoses (17 through 20) to counterbalance valve
(21).
c. Follow-On Maintenance.
(1) Install boom assembly (para 16-3).
(2) Check fluid level in hydraulic reservoir. Refill as required
(TM 9-2320-366-20).
(3) Perform crane load test (para 16-31).
End of Task.