TM 9-2320-366-34-3
NOTE
Left and right side hydraulic hoses are
installed the same way. Left side shown.
(11) Install two fittings (14) and nuts (15) on mast (1).
(12) Install hoses (16 and 17) on fittings (14).
(13) Install four clamps (18) and eight screws (19) on mast
(1).
(14) Perform steps (11) through (13) on right side hoses (16
and 17).
c. Follow-On Maintenance.
(1) Install lift cylinders (para 16-37).
(2) Install boom assembly (para 16-33).
(3) Place hydraulic reservoir supply and return valves in
open position (TM 9-2320-366-10-2).
(4) Perform crane load test (para 16-62).
End of Task.
16-227