TM 9-2320-366-34-3
16-46. M1089 TENSION LOAD CELL REPLACEMENT
This task covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Equipment Conditions
Boom positioned over tool boxes (TM 9-2320-366-10-
2).
Batteries disconnected (TM 9-2320-366-20-3).
Tools and Special Tools
Tool Kit, Genl Mech (Item 78, Appendix B)
Bar, Wrecking (Item 6, Appendix B)
Sling, Cargo (Item 56, Appendix B)
Materials/Parts
Cap and Plug Set (Item 17, Appendix C)
Materials/Parts (Cont)
Packing, Preformed (2) (Item 231, Appendix F)
Packing, Preformed (Item 261, Appendix F)
Sealing Compound (Item 76, Appendix C)
Ties, Cable Plastic (Item 92, Appendix C)
Lockwasher (Item 138, Appendix F)
Dispenser, Pressure Sensitive Adhesive Tape
(Item 30, Appendix C)
Personnel Required
(2)
a. Removal.
NOTE
· Tag electrical connectors and connection
points prior to disconnecting.
· Remove plastic cable ties as required.
(1) Disconnect tension load cell connector (1) from overload
shutdown box (2).
(2) Disconnect proximity sensor connector (3) from overload
shutdown box (2).
16-247