TM 9-2320-366-34-3
(2) Install overload shutdown (7) and ground strap (2) on
boom assembly (3) with washer (8), lockwasher (9), and
bolt (10).
(3) Install washer (11), lockwasher (12), and bolt (13) on
overload shutdown (7).
NOTE
Step (4) requires the aid of an assistant.
(4) Install two clipnuts (14), washers (15), lockwashers (16),
and bolts (17) in overload shutdown (7).
(5) Connect three connectors (18) to overload shutdown (7).
(6) Connect cable eye (19) to bolt (20).
c. Follow-On Maintenance.
(1) Connect batteries (TM 9-2320-366-20-3).
(2) Perform crane load test (para 16-31).
End of Task.
16-109